Transportation Project Updates

Below are projects in pre-construction or construction at Cobb DOT.  Links to travel advisories/lane closures and SPLOST project fact sheets are provided, if available, for each project as well as significant travel advisories, project descriptions and a project contact.

2019 Countywide ADA Sidewalks District 1 and 2 (Project No. X2782A – 2016 SPLOST)

These projects include sidewalk and pedestrian ramp improvements within Commission Districts 1 and 2 to ensure compliance with ADA Standards.

Cobb DOT Project Manager

Brian Loudermilk
(770) 528-4378
[email protected]

District 1 Locations

Cochran Road at Knox Drive

6002 Armor Drive

6010 Armor Drive

5839 Fairwood Walk

5708 Fairwood Walk

888 Foxwerthe Drive

2451 Huntington Park Drive

418 Wallis Farm Way

422 Wallis Farm Way

442 Wallis Farm Way

454 Wallis Farm Way

2668 Lakefield Pass

2676 Lakefield Pass

1622 Arbor Green Court

1644 Arbor Green Court

Shiloh Road & Hickory Grove Road

1276 Rolling Oaks Drive

1328 Rolling Oaks Drive

District 2 Locations

Cumberland Club Drive at Mt. Wilkinson

Reed Road at Hidden Springs Trace and King Springs Road

4450 Ivy Glen Drive

66 Coopers Glen Drive

3110 Brandy Station

3340 Paces Mill Road

2630 Beckwith Trail

3401 Robinson Road

3774 Baccurate Way

559 Lullingstone Drive

573 Lullingstone Drive

589 Lullingstone Drive

605 Lullingstone Drive

515 Stepney Court

3661 Wyntering Trail

3052 Prentiss Point

4348 Sprucebough Drive

2973 Black Bear Drive

Johnson Ferry Road & Sewell Mill Road

1772 Johnson Ferry Road

4413 Summit Oaks Place

3991 Chapel Grove Drive

3975 Chapel Grove Drive

Acworth Due West Road at Jim Owens Road/Mars Hill Church Road (Project No. X2301 – 2016 SPLOST)

View Travel Advisories/Lane Closures

Lane closures are possible Monday - Friday from 9 a.m. to 4 p.m.

View 2016 SPLOST Fact Sheet

This project was combined for construction with Jim Owens Road - Lewis Elementary School (X2801) due to their proximity. 

The combined project consists of the construction of a roundabout at the intersection of Acworth Due West Road and Jim Owens Road/Mars Hill Church Road to replace the existing 4-way stop. The project also includes the installation of sidewalks, a deceleration lane, and driveway improvements at Lewis Elementary School.

This project is scheduled to be completed in the spring of 2021.

Cobb DOT Project Manager

Brian Loudermilk
(770) 528-4378
[email protected]

Beech Road - Westside Drive (Project No. X2601 – 2016 SPLOST)

View Travel Advisories/Lane Closures

Lane closures are possible on Westside Drive from South Cobb Drive to Sandtown Road,  Monday - Friday from 9 a.m. to 4 p.m.

Image
Picture of Beech Road at Westside Drive

View 2016 SPLOST Fact Sheet

This project includes construction of a roundabout at the intersection of Westside Drive and Sandtown Road, to include a new two-lane roadway with curb and gutter and sidewalk extending to South Cobb Drive. At the intersection of Westside Drive and South Cobb Drive, the Westside Drive approach will include dual left turn lanes and a right turn lane. The existing traffic signal at Beech Road and South Cobb Drive will be removed, and a new traffic signal will be installed at South Cobb Drive and Westside Drive. This project is scheduled to be completed in the spring of 2020.

Cobb DOT Project Manager

John Morey
(770) 528-1661
[email protected]

Bells Ferry Road Sidewalk (Project No. X2745 – 2016 SPLOST)

View Travel Advisories/Lane Closures

Lane closures are possible Monday - Friday from 9 a.m. to 4 p.m.

View 2016 SPLOST Fact Sheet

This project includes construction of eight-foot wide sidewalk with curb and gutter on the west side of Bells Ferry Road, from Noonday Creek trailhead driveway to Big Shanty Road. This project is scheduled to be completed in the spring of 2020.

Cobb DOT Project Manager

Brian Loudermilk
(770) 528-4378
[email protected]

Big Shanty Road Sidewalk Improvements (Project No. D7280 – 2005 SPLOST)

View Travel Advisories/Lane Closures

Image
Picture of construction activities on project

Lane closures are possible Monday - Friday from 9 a.m. to 4 p.m.

This project includes construction of ten-foot wide sidewalk with curb and gutter on the south side of Big Shanty Road from Chastain Meadows Parkway to Bells Ferry Road. This project is scheduled to be completed in the summer of 2020.

Cobb DOT Project Manager

Brian Loudermilk
(770) 528-4378
[email protected]

Big Shanty Road Sidewalk (Project No. X2704 – 2016 SPLOST)

View Travel Advisories/Lane Closures

View 2016 SPLOST Fact Sheet

This project is scheduled to be constructed concurrently with McCollum Parkway at Ben King Road (Project No. X2309) and McCollum Parkway Sidewalk (Project No. E7350) due to their proximity and to minimize impacts to traveling public.  

This project consists of installing sidewalk along the northern side of Big Shanty Road from McCollum Parkway to Chastain Road.

Construction for this project is scheduled to begin in the spring of 2020.

Cobb DOT Project Manager

Brian Loudermilk
(770) 528-4378
[email protected]

Blackwell Road at Autumn Ridge Parkway (Project No. X2302 – 2016 SPLOST)

View Travel Advisories/Lane Closures

Image
Picture of construction activities on project

Autumn Ridge Parkway will be closed from January 6, 2019 to March 6, 2019 as roadway grade changes are completed. Drivers should follow posted detour. Additional lane closures possible Monday - Friday from 9 a.m. to 4 p.m. until project completion.

View 2016 SPLOST Fact Sheet

This project includes sight distance improvements and removal of existing four-way stop at the intersection of Blackwell Road and Autumn Ridge Parkway, creating a two-way stop. Additional improvements include construction of left turn lanes in both directions on Blackwell Road to Autumn Ridge Parkway, and also includes the addition of curb and gutter, with a five-foot wide sidewalk. This project is scheduled to be completed in the summer of 2020.

Cobb DOT Project Manager

Brian Loudermilk
(770) 528-4378
[email protected]

Bob Callan Trunk Trail / Phase 2 Segment B (Project No. D11M0 – 2005 SPLOST)

Phase 2 of this trail project was initiated by the Cumberland Community Improvement District (CCID) as a single project to provide an extension of the existing network of trails in the Cumberland Galleria area by adding a 10-foot wide trail from Interstate North Parkway to Terrell Mill Road. The total length of this project was approximately 2.1 miles. 

The Georgia Department of Transportation (GDOT) approved a revised concept in July 2013 to separate Phase 2 of this project into two segments. Segment A begins at the existing Bob Callan Trailhead on Interstate North Parkway and ends at the Interstate North Parkway crossing of Rottenwood Creek.  Segment B continues along Rottenwood Creek to Terrell Mill Road. 

Bob Callan Trunk Trail, Phase 2, Segment B, was previously evaluated and designed based on an alignment along Rottenwood Creek. Due to identified utility and constructability conflicts discovered during the design, the alignment has been modified, resulting in the need to redesign the project.

Cobb DOT Project Manager

Russ Ford
(770) 420-6659
[email protected]

Buckner Road Sidewalk (Project No. 2766 – 2016 SPLOST)

View 2016 SPLOST Fact Sheet

This project consists of constructing curb and gutter with a five-foot wide sidewalk along the western side of Buckner Road from Veterans Memorial Highway to Kilrush Drive (0.95 miles), and along the eastern side from Veterans Memorial Highway to Rosie Lane (0.74 miles). The total length of the project is estimated at 1.69 miles.

Cobb DOT Project Manager

John Morey
(770) 528-1661
[email protected]

Campus Loop Road/Big Shanty Road/Chastain Road (Project No. X2303 – 2016 SPLOST)

Public Information Open House Welcome Packet (Handouts from PIOH at Pinetree Country Club on 1/16/2020)

View 2016 SPLOST Fact Sheet

The project consists of operational improvements at the intersection of Campus Loop Road and Big Shanty Road, while considering the potential impacts to the adjacent intersection of Big Shanty Road and Chastain Road. The improvements may require the realigning of Campus Loop Road to reduce congestion and improve connectivity. The project will take into consideration the context of the area, the need for pedestrian crossings, and vehicular movements.

Cobb DOT Project Manager

Brian Loudermilk
(770) 528-4378
[email protected]

Canton Road Corridor/Canton Road at Liberty Hill (Project No. X2602 – 2016 SPLOST)

View Travel Advisories/Lane Closures

Lane closures are possible Monday - Friday from 9 a.m. to 4 p.m.

View 2016 SPLOST Fact Sheet

This project consists of intersection improvements to include construction of a southbound deceleration/right turn lane into the RaceTrac development, left turn striping into the RaceTrac development, and traffic signal modifications to the existing signal. This project falls within the limits of the Canton Road Corridor project - X2602. This project is scheduled to be completed in January 2020.

Cobb DOT Project Manager

Karyn Matthews
(770) 528-3685
[email protected]

Canton Road at Shallowford Road (Project No. X2304 – 2016 SPLOST)

View 2016 SPLOST Fact Sheet

This project includes the addition of a right-turn lane to the northbound side of Canton Road.

Cobb DOT Project Manager

Karyn Matthews
(770) 528-3685
[email protected]

Cherokee Street Improvements (Project No. X2603 – 2016 SPLOST)

View Travel Advisories/Lane Closures

Image
Picture of construction activities on project

Lane closures are possible Monday - Friday from 9 a.m. to 4 p.m.

View 2016 SPLOST Fact Sheet

This project includes construction of a third travel lane on Cherokee Street in the eastbound direction only, the addition of a right turn lane at the intersection of Shiloh Road, and access improvements within the project limits. This project is scheduled to be completed in the summer of 2021.

Cobb DOT Project Manager

Brian Loudermilk
(770) 528-4378
[email protected]

Chimney Springs Sidewalk (Project No. X2727 – 2016 SPLOST)

View Travel Advisories/Lane Closures

Image
Picture of construction activities on project

View 2016 SPLOST Fact Sheet

This project includes construction of a five-foot wide sidewalk along the west side of Chimney Springs Drive, from Revere Circle to Bishop Lake. This project is scheduled to be completed in November 2019.

Cobb DOT Project Manager

Ligia Florim
[email protected]

Dallas Highway at Lost Mountain/Mars Hill Road (Project No. X2305 – 2016 SPLOST)

View 2016 SPLOST Fact Sheet

The project consists of intersection improvements on SR 120/Dallas Highway from McConnell Road to Schofield Drive, on Mars Hill Road from Dallas Highway to Pindos Pass and Collegiate Way, and on Lost Mountain Road from Dallas Highway to approximately 1100 feet south of the intersection.  Improvements include lengthening of the eastbound and westbound left-turn lanes, reassignment of lanes on the northern leg, and widening/reassignment of lanes on the southern leg.

Cobb DOT Project Manager

Ligia Florim
[email protected]

Ebenezer Road Sidewalk (Project No. X2743 – 2016 SPLOST)

View 2016 SPLOST Fact Sheet

This project includes the a addition of five-foot wide sidewalk along the eastern side of Ebenezer Road from Hampton Oaks Bend to Maybreeze Road. This project also includes the addition of a five-foot wide sidewalk on the southern side of Maybreeze Road between Ebenezer Road and Corye Lane to close gaps and connect missing segments with existing sidewalk. Curb and gutter will be added where none exists.

Cobb DOT Project Manager

Brian Loudermilk
(770) 528-4378
[email protected]

Factory Shoals Road and Beverly Drive Improvements (Harmony Leland/Clay Elementary School) Phase 1 and Phase 2 (Project No X2807 – 2016 SPLOST)

View Travel Advisories/Lane Closures

Image
Picture of construction activities on project

Lane closures are possible Monday - Friday from 9 a.m. to 4 p.m.

View 2016 SPLOST Fact Sheet

This project consists of school zone safety and operational improvements on Factory Shoals Road and Beverly Drive in coordination with construction of the Cobb County School District (CCSD) Harmony Leland and Clay Elementary Schools relocation project. Beverly Drive improvements include minor widening and pedestrian enhancements between Factory Shoals Drive and Elizabeth Lane. Factory Shoals Road improvements consist of creating a left-turn lane at the main school driveway in conjunction with school zone traffic control devices. CCSD will provide roadway improvements along the school site frontage on both Factory Shoals Road and Beverly Drive. This project is scheduled to be completed in the summer of 2020.

Cobb DOT Project Manager

Dave Garrett
(770) 420-6654
[email protected]

Factory Shoals Road at Riverside Parkway (Project No. X2306 – 2016 SPLOST)

View Travel Advisories/Lane Closures

View 2016 SPLOST Fact Sheet

This project consists of intersection improvements, including the addition of a right-turn lane from northbound Factory Shoals Road onto eastbound Riverside Parkway. Also included is the installation of a new traffic signal and pedestrian improvements. Construction for this project is scheduled to begin in January 2020.

Cobb DOT Project Manager

Ligia Florim
[email protected]

Favor Road at Windy Hill Road (Osborne High School) (Project No. X2806 – 2016 SPLOST)

View Travel Advisories/Lane Closures

Image
Picture of construction activities on project

Lane closures are possible Monday - Friday from 9 a.m. to 4 p.m.

View 2016 SPLOST Fact Sheet

This project includes school zone improvements on both Favor Road and Windy Hill Road, in conjunction with the Cobb County School District (CCSD) project to rebuild Osborne High School and construct the new Cobb Career Academy.  Improvements are designed to enhance traffic flow in the area and increase queuing capacity at Osborne High School. Improvements will also provide additional ingress and egress for Osborne High School, as well as the adjacent Academy. Also included are pedestrian improvements that will connect with improvements being constructed on school property. This project is scheduled to be completed in the summer of 2020.

Cobb DOT Project Manager

Dave Garrett
(770) 420-6654
[email protected]

Gordon Combs Road Sidewalk (Project No. E7580 – 2011 SPLOST)

View Travel Advisories/Lane Closures

Lane closures are possible Monday - Friday from 9 a.m. to 4 p.m.

View 2011 SPLOST Fact Sheet

This project consists of constructing a five-foot wide sidewalk with curb and gutter on the east side of Gordon Combs Road from Burnt Hickory Road to Madison Grove Lane. This project is scheduled to be completed in the summer of 2020.

Cobb DOT Project Manager

Brian Loudermilk
(770) 528-4378
[email protected]

Hicks Road at Concord Road (Project No. X2307 – 2016 SPLOST)

View Travel Advisories/Lane Closures

Lane closures are possible Monday - Friday from 9 a.m. to 4 p.m.

Image
Picture of construction activities for project

View 2016 SPLOST Fact Sheet

This project includes improvements to the intersection of Hicks Road and Concord Road including lane   additions, traffic signal modifications, drainage improvements, and sidewalk additions. This project is scheduled to be completed in the spring of 2021.

Cobb DOT Project Manager

John Morey
(770) 528-1661
[email protected]

Hillcrest Drive Sidewalk (Project No. X2764 – 2016 SPLOST)

View 2016 SPLOST Fact Sheet

This project consists of adding curb and gutter with a five-foot wide sidewalk along both sides of Hillcrest Drive from South Gordon Road to Six Flags Parkway.  Additionally, curb and gutter with a five-foot wide sidewalk will be added on the northern side of Six Flags Parkway from Hillcrest Drive to Silver Mine Trail.  The total length of the project is estimated at 1.60 miles.

Cobb DOT Project Manager

John Morey
(770) 528-1661
[email protected]

I-20 EB Ramps at Riverside Parkway (Project No. X2409 – 2016 SPLOST)

View Travel Advisories/Lane Closures

Lane closures are possible on Riverside Parkway, Monday - Friday from 9 a.m. to 4 p.m.

Image
Picture of construction activities for project

View 2016 SPLOST Fact Sheet

This project includes construction of an additional right turn lane from I-20 eastbound off-ramp onto Riverside Parkway, and realignment of the South Service Drive intersection with Riverside Parkway from the existing location to 360 feet south, to tie into the existing Riverside EpiCenter driveway access point. Improvements within the project limits include installation of new traffic signals, raised medians, sidewalks, resurfacing and other pedestrian improvements. In addition, the project will provide directional way-finding signage both overhead and roadside along both I-20 eastbound and westbound lanes, the I-20 eastbound off-ramp, Riverside Parkway and South Service Drive to direct traffic to Six Flags Over Georgia. This project is scheduled to be completed in December 2020.

Cobb DOT Project Manager

Ligia Florim
[email protected]

Jim Owens Road - Lewis Elementary (Project No. X2801 – 2016 SPLOST)

View Travel Advisories/Lane Closures

View 2016 SPLOST Fact Sheet

This project was combined for construction with Acworth Due West Road at Jim Owens/Mars Hill Church Roads (X2301) due to their proximity. 

The combined project consists of the construction of a roundabout at the intersection of Acworth Due West Road and Jim Owens Road/Mars Hill Church Road to replace the existing 4-way stop. The project also includes the installation of sidewalks, a deceleration lane, and driveway improvements at Lewis Elementary School. 

This project is scheduled to be completed in the spring of 2021.

Cobb DOT Project Manager

Brian Loudermilk
(770) 528-4378
[email protected]

John Ward Road Sidewalk (Project No. X2702 – 2016 SPLOST)

View Travel Advisories/Lane Closures

Image
Picture of construction activities on project

Lane closures are possible Monday - Friday from 9 a.m. to 4 p.m.

View 2016 SPLOST Fact Sheet

This project includes construction of a sidewalk on the west side of John Ward Road from Macland Road to Irwin Road. This project is scheduled to be completed in November 2019.

Cobb DOT Project Manager

Brian Loudermilk
(770) 528-4378
[email protected]

Kennesaw Mountain Pedestrian Improvements/Cheatham Hill Multi-use Trail (Project No. X2404 – 2016 SPLOST)

View 2016 SPLOST Fact Sheet

Kennesaw Mountain Pedestrian Improvements, also known as Cheatham Hill Multi-Use Trail, is a joint project with the City of Marietta.  This project consists of improvements to the trail network in the Kennesaw Mountain National Battlefield Park area. Improvements include construction of eight-foot (minimum) to ten-foot (desired) wide multi-use trails in the following locations: along Cheatham Hill Road (from Powder Springs Road to the existing trail near John Ward Road); along Whitlock Avenue (from the intersection of John Ward Road and Whitlock Avenue/Dallas Highway/SR120 to Cheatham Hill Drive) and along Burnt Hickory Road (from Whitlock Avenue to Old Mountain Road). 

Cobb DOT Project Manager

James Hudgins
(770) 420-6658
[email protected]

Kinjac Drive Sidewalk (Project No. X2750 – 2016 SPLOST)

View 2016 SPLOST Fact Sheet

This project consists of adding a five-foot wide sidewalk along the eastern side of Kinjac Drive from Sandy Plains Road to Macby Drive. The total length of the project is estimated at 0.40 miles.

Cobb DOT Project Manager

Brian Loudermilk
(770) 528-4378
[email protected]

Lost Mountain Road at Midway Road/Mirror Lake Drive (Project No. X2308 – 2016 SPLOST)

View Travel Advisories/Lane Closures

Lane closures are possible Monday - Friday from 9 a.m. to 4 p.m.

Image
Picture of Lost Mountain Road at Midway construction activities

View 2016 SPLOST Fact Sheet

This project includes realignment of the intersection of Lost Mountain Road and Midway Road to create a four-way signalized intersection with Lost Mountain Road and Mirror Lake Drive.  Additional turn lanes will be added to support the increase in turning movements. This project is scheduled to be completed in the fall of 2020.

Cobb DOT Project Manager

Brian Loudermilk
(770) 528-4378
[email protected]

Mableton Parkway Pedestrian Improvements (Project No. X2762 – 2016 SPLOST)

View 2016 SPLOST Fact Sheet

This project includes construction of a ten-foot wide trail on the western side of Mableton Parkway and a five-foot sidewalk on the eastern side from Factory Shoals Road to Discovery Boulevard.  Traffic signal upgrades are also included at signalized intersections within the project limits.

Cobb DOT Project Manager

Brian Loudermilk
(770) 528-4378
[email protected]

Mack Dobbs Road (Project No. 2606 – 2016 SPLOST)

View 2016 SPLOST Fact Sheet

This joint project with the City of Kennesaw includes roadway safety and traffic operational improvements on Mack Dobbs Road from Caylor Circle to Cobb Parkway (US 41).  Improvements will include turn lanes, sidewalks, curb and gutter, and drainage improvements.

Cobb DOT Project Manager

Ligia Florim
[email protected]

Mars Hill Road over Allatoona Creek (Project No. X2115 – 2016 SPLOST)

View 2016 SPLOST Fact Sheet

Mars Hill Road over Allatoona Creek improvements include the replacement of the deficient bridge located on Mars Hill Road between Chipping Drive and Waldenbrooke Court.

Cobb DOT Project Manager

Karyn Matthews
(770) 528-3685
[email protected]

McCollum Parkway at Ben King Road (Project No. X2309 – 2016 SPLOST)

View Travel Advisories/Lane Closures

View 2016 SPLOST Fact Sheet

This project is scheduled to be constructed concurrently with Big Shanty Road Sidewalk (Project No. X2704) and McCollum Parkway Sidewalk (Project No. E7350) due to their proximity and to minimize impacts to traveling public.

McCollum Parkway at Ben King Road is an approved intersection improvements project in the 2016 SPLOST. This joint project with the City of Kennesaw consists of intersection improvements on McCollum Parkway at Ben King Road and Big Shanty Road, including construction of a roundabout at the intersection of McCollum Parkway at Ben King Road.  Also included are the addition of turn lanes and road realignment of Lockhart Drive and McCollum Parkway. Construction for this project is scheduled to begin in the spring of 2020.

Cobb DOT Project Manager

Brian Loudermilk
(770) 528-4378
[email protected]

McCollum Parkway Sidewalk (Project No. E7350 – 2011 SPLOST)

View Travel Advisories/Lane Closures

View 2011 SPLOST Fact Sheet

This project This project is scheduled to be constructed concurrently with Big Shanty Road Sidewalk (Project No. X2704) and McCollum Parkway at Ben King Road (Project No. X2309) due to their proximity and to minimize impacts to traveling public.

McCollum Parkway Sidewalk (also known as McCollum Parkway Multi-use Trail) is an approved pedestrian improvements project in the 2011 SPLOST.  The project consists of constructing a multi-use trail along the western side of McCollum Parkway from Ben King Road to Olympic Lane.

Construction for this project is scheduled to begin in the spring of 2020.

Cobb DOT Project Manager

Brian Loudermilk
(770) 528-4378
[email protected]

New Macland Road (Project No. X2608 – 2016 SPLOST)

View Travel Advisories/Lane Closures

View 2016 SPLOST Fact Sheet

The project consists of roadway safety and traffic operational improvements on New Macland Road from Arapaho Drive to Macland Road. Improvements include construction of turn lanes and sidewalks and replacement of two culverts.  Project limits encompass McEachern High School frontage on New Macland Road.  Construction for this project is scheduled to begin in the spring of 2020.

Cobb DOT Project Manager

Ligia Florim
[email protected]

Old Canton Road at Holly Springs Road (Project No. X2310 – 2016 SPLOST)

View 2016 SPLOST Fact Sheet

This project consists of safety improvements at the intersection of Old Canton Road and Holly Springs Road. Additional project activities include resurfacing from Old Canton to Sandy Plains Road, restriping to add turn lanes where needed, and installing median islands to discourage improper use of the center turn lane.

Cobb DOT Project Manager

Karyn Matthews
(770) 528-3685
[email protected]

Old Highway 41 over CSX Railroad (Project No. X2116 – 2016 SPLOST)

View Travel Advisories/Lane Closures

Image
Picture of construction activities on project

Lane closures are possible Monday - Friday from 9 a.m. to 4 p.m.

View 2016 SPLOST Fact Sheet

This project includes complete bridge replacement of the existing bridge located on Old 41 Highway over the CSX Railroad, near the intersection of Bells Ferry Road. This project is scheduled to be completed in the summer of 2021.

Cobb DOT Project Manager

Karyn Matthews
(770) 528-3685
[email protected]

Paces Ferry Road Improvements/Paces Ferry Road Sidewalk at CSX (Project No. X2318/X2726 – 2016 SPLOST)

View Travel Advisories/Lane Closures

A new traffic flow has been implemented permanently in the Vinings area at the Paces Ferry Road/Paces Mill Road intersection (read more).

Lane closures are possible Monday - Friday from 9 a.m. to 4 p.m.

Image
Picture of construction activities for project

View 2016 SPLOST Fact Sheet (X2318)

View 2016 SPLOST Fact Sheet (X2726)

These projects were combined for construction due to their proximity.

Paces Ferry Road improvements consist of the addition of a left turn lane on Paces Ferry Road at New Paces Ferry Road, and the addition of concrete islands at Twin Lakes Drive. The project also includes reconstruction of three traffic signals, as well as filling in the gaps between existing sidewalks. Gaps will be filled on the southern side of Paces Ferry Road from Twin Lakes Drive to Paces Mill Road, and on the western side of New Paces Ferry Road from Paces Ferry Road to Tanglewood Drive.  

Paces Ferry Road Sidewalk at CSX consists of filling in the gaps between existing sidewalks on both the north and south sides of Paces Ferry Road at the CSX railroad crossing.  The project also includes the addition of new sidewalks and relocation of the north crossing gates.

This project is scheduled to be complete in the spring of 2020.

Cobb DOT Project Manager

Karyn Matthews
(770) 528-3685
[email protected]

Post Oak Tritt at Hembree Road (Pope High School)

View Travel Advisories/Lane Closures

Image
Picture of construction activities on project

Lane closures are possible Monday - Friday from 9 a.m. to 4 p.m.

View 2016 SPLOST Fact Sheet

This project consists of constructing a roundabout at the intersection of Post Oak Tritt Road and Hembree
Road. Improvements include enhanced street lighting and sidewalk ramp upgrades to comply with current
Americans with Disabilities Act standards. This project is scheduled to be complete in the spring of 2020.

Cobb DOT Project Manager

David Garrett
770-420-6654
[email protected]

Powers Ferry Drive over Rottenwood Creek Tributary (Project No. X2118 – 2016 SPLOST)

View Travel Advisories/Lane Closures

View 2016 SPLOST Fact Sheet

The project consists of replacing the existing bridge over Rottenwood Creek with a triple 8-foot by 8-foot culvert.  Construction for this project is scheduled to begin in February 2020.

Cobb DOT Project Manager

Karyn Matthews
(770) 528-3685
[email protected]

Railroad Quiet Zone Improvements (Project No. X2313 – 2016 SPLOST)

View 2016 SPLOST Fact Sheet

This is a joint project with the City of Smyrna to create a railroad quiet zone at Nickajack Road. Quiet zones eliminate the need for the train engineer to sound the train horn at railroad crossings once the necessary safety improvements are made.  Based on the initial review of the site by personnel from Norfolk Southern Railway (NSR), the Federal Railroad Administration, and the Georgia Department of Transportation, this site will require the installation of four quadrant gates.   

This project is being managed by Norfolk Southern Railway (NSR), the governing railroad at this crossing. In accordance with Federal Railroad Administration’s Guide to the Quiet Zone Establishment process, NSR will prepare preliminary engineering/design plans and other related construction documents for the project.

Cobb DOT Project Manager

Russ Ford
(770) 420-6659
[email protected]

Resurfacing

Projects include resurfacing on various county streets, including variable depth milling, patching, leveling, resurfacing and pavement markings as well as crack sealing/resurfacing of the Cobb County Safety Village.

Travel Advisories/Lane Closures

DAYTIME Resurfacing Operations – Expect lane closures from 9 a.m. to 4 p.m., Monday-Friday (some Saturday closures are possible) with one lane remaining open at all times on the following road(s):

Chimney Springs Drive between Bishop Lake Road and Bishop Lake Road

Clubland Drive from Indian Hills Drive to Indian Hills Drive – Patching Only

Indian Hills Parkway from Lower Roswell Road to Roswell Road – Patching Only

Interstate West Parkway

John Ward Road from Irwin Road to Cheatham Hill Road

Shallowford Road between Canton Road and Trickum Road

Terrell Mill Road from Greenwood Trail to Powers Ferry Road

(The above scheduled resurfacing work is subject to change due to weather or construction progress.)

Cobb DOT Project Manager

Kristen Orton
(678) 581-3428
[email protected]

Riverview Road (Project No. E6040 – 2011 SPLOST)

View Travel Advisories/Lane Closures

Lane closures are possible Monday - Friday from 9 a.m. to 4 p.m.

Image
Picture of River View Road

View 2011 SPLOST Fact Sheet

This project includes safety and operational improvements along Riverview Road, from Veterans Memorial Highway to the Smyrna City Limit boundary line near Nichols Drive.  The project will realign the intersection at River View Road with Veterans Memorial Highway. This project is scheduled to be completed in the fall of 2020.

Cobb DOT Project Manager

Ligia Florim
[email protected]

Sandtown Road (Project No. X2610 – 2016 SPLOST)

View 2016 SPLOST Fact Sheet

This joint project with the City of Marietta consists of roadway safety and traffic operational improvements along Sandtown Road from Austell Road to Westside Drive. This project includes adding turn lanes, sidewalks, and curb and gutter in addition to traffic signal enhancements and drainage improvements.

Cobb DOT Project Manager

Ligia Florim
[email protected]

Sandy Plains Road (Project No. E6060 – 2011 SPLOST)

View Travel Advisories/Lane Closures

Image
Picture of construction activities on project

Daily lane closures are possible in both directions between Kinjac Drive and Ebenezer Road, north of Piedmont Road. Drivers are advised to take Canton Road or Holly Springs Road as alternate routes to avoid traffic congestion. Motorists using Sandy Plains Road should reduce their speed and exercise caution in the area.

View 2011 SPLOST Fact Sheet

This project includes installation of raised concrete median, from Kinjac Drive to Ebenezer Road, with   appropriate median cuts and access points. Other improvements include new crosswalks and pedestrian signalization, new traffic signalization, and resurfacing of Sandy Plains Road. Also included are widened sections, associated pavement markings, and signage. This project is scheduled to be completed in December 2019.

Cobb DOT Project Manager

Karyn Matthews
(770) 528-3685
[email protected]

Shiloh Road at Royal Drive (Project No. X2314 – 2016 SPLOST)

View 2016 SPLOST Fact Sheet

This project consists of safety and operational improvements at the intersection of Shiloh Road and Royal Drive/Apartment Drive, including signalization of the intersection and reassignment of lanes.

Cobb DOT Project Manager

Karyn Matthews
(770) 528-3685
[email protected]

Silver Comet Trail Bridges (Project No. X2119 – 2016 SPLOST)

Travel Advisory

Image
Picture of construction activities on project

Noses Creek Trail Bridge: The Silver Comet Trail bridge over Noses Creek, located near the Carter Road

parking lot and trail mile marker 8.4 will be closed from Monday, January 6, 2020 to Thursday, February
20, 2020. The Wildhorse Creek Trail will remain open with the potential for temporary closures and flagging
under the Silver Comet Trail bridge. Parts of the Carter Road parking lot will be closed for construction
equipment/supplies.

There will be no access through the construction site during the closures and no detours will be
available.

View 2016 SPLOST Fact Sheet

This project includes repair of two existing bridges located on the Silver Comet Trail. Repairs on the bridge over Nickajack Creek include replacement of the bridge railing and footing repairs. Repairs on the bridge over Noses Creek include replacement of the bridge deck, wood pile, and pile encasements, as well as installation of a bridge deck drainage system.

Cobb DOT Project Manager

James Hudgins
(770) 420-6658
[email protected]

South Barrett Reliever Phase 3 (Project No. X2407 – 2016 SPLOST)

View 2016 SPLOST Fact Sheet

The South Barrett Reliever project will provide an alternate route for the public traveling to the highly developed office, commercial, and residential areas at I-75, as well as those motorists accessing I-75 at Barrett Parkway.  

Phase 3 of the project consists of the extension and widening of Shiloh Valley Drive/Greers Chapel Drive across Interstate 75 (I-75), terminating at the intersection of Roberts Court and Barrett Parkway. Proposed improvements include construction of a bridge with no interstate access over I-75, and the addition of a roundabout at Greers Chapel Drive and Roberts Court. The total project length of Phase 3 is approximately 0.81 miles.

Cobb DOT Project Manager

Brian Loudermilk
(770) 528-4378
[email protected]

West Atlanta Street Trail (Project No. X2412 – 2016 SPLOST)

View 2016 SPLOST Fact Sheet

This project includes construction of a twelve-foot wide multi-use trail, five-foot wide grass strip, and curb and gutter along the eastern side of West Atlanta Street. The project will also fill in the current gap within a segment of existing trail.

Cobb DOT Project Manager

John Morey
(770) 528-1661
[email protected]

Willeo Road over Willeo Creek (Project No. X2122 – 2016 SPLOST)

View 2016 SPLOST Fact Sheet

This joint project with the City of Roswell includes a complete replacement of the existing bridge over Willeo Creek located on Willeo Road between Bywater Trail and Timber Ridge Road/Lower Roswell Road at the Cobb/Fulton County line.

Cobb DOT Project Manager

Karyn Matthews
(770) 528-3685
[email protected]

Windy Hill Road / Bridge Repair over Rottenwood Creek (Project No. E4020 – 2011 SPLOST)

View Travel Advisories/Lane Closures

Image
Picture of construction activities on project

Lane closures are possible on Windy Hill Road from Interstate North Parkway to Leland Drive, Monday - Friday from 9 a.m. to 4 p.m.

View 2011 SPLOST Fact Sheet

This project includes bridge deck patching, replacement of deck joints, pile encasement, installation of polymer overlay, extension of the existing gabion wall, and installation of riprap to the existing bank. This project is scheduled to be completed in the spring of 2020.

Cobb DOT Project Manager

James Hudgins
(770) 420-6658
[email protected]

Windy Hill Road/Windy Hill Boulevard (Project No. X2402 – 2016 SPLOST)

View Travel Advisories/Lane Closures

Lane closures are possible on Windy Hill Road from South Cobb Drive to Atlanta Road, Monday - Friday from 9 a.m. to 4 p.m.

View 2016 SPLOST Fact Sheet

This joint project, being managed and led by the City of Smyrna, consists of a roadway expansion as well as intersection and pedestrian improvements to the portion of Windy Hill Road that runs from South Cobb Drive to Atlanta Road, which will be known as Windy Hill Boulevard.   

For information on this project, please contact the Smyrna Public Works Department at (770) 431-2850 or visit the City of Smyrna website

Windy Hill/ Terrell Mill Connector (Project No. X2401 – 2016 SPLOST)

View Travel Advisories/Lane Closures

View 2016 SPLOST Fact Sheet

The project consists of a new thoroughfare between Windy Hill Road and Terrell Mill Road.  The new thoroughfare will begin at the intersection of Windy Hill Road and Spectrum Circle, and continue north to the intersection of Terrell Mill Road and Bentley Road.  This will be a new four-lane road with a raised center median and will include sidewalk and a multi-use trail. The total project is approximately 0.70 miles in length. Construction for this project is scheduled to begin in January 2020.

Cobb DOT Project Manager

Karyn Matthews
(770) 528-3685
[email protected]

Windy Ridge Parkway Sidewalk (Project No. X2724 – 2016 SPLOST)

View 2016 SPLOST Fact Sheet

This project includes widening the sidewalk on Windy Ridge Parkway between Cobb Parkway and Heritage Court to trail width.

Cobb DOT Project Manager

Karyn Matthews
(770) 528-3685
[email protected]

Woodland Brook Drive Drainage (Project No. X2260 – 2016 SPLOST)

View 2016 SPLOST Fact Sheet

This project consists of repairing a failing 24-inch culvert and pavement in the vicinity of 4292 Woodland Brook Drive.

Cobb DOT Project Manager

John Morey
(770) 528-1661
[email protected]

Woodland Brook Drive over Vinings Branch Bridge Replacement (Project No.  X2120 – 2016 SPLOST)

View Travel Advisories/Lane Closures

Travel lanes on this bridge have been modified to reduce traffic flow from two lanes to one lane. This change will remain in effect until the bridge is closed for construction in the summer of 2020.  A temporary traffic signal has been installed to assist cars crossing the bridge.

View 2016 SPLOST Fact Sheet

The project consists of a complete replacement of the deficient bridge crossing over Gilmore Creek (Vinings Branch) with a box culvert. Construction for this project is scheduled to begin in the summer of 2020.

Cobb DOT Project Manager

Ligia Florim
[email protected]