 Cobb DOT and Cobb County-Marietta Water Authority have projects that will require closing three roads this summer. All closures are expected to start on June 1, 2021 and continue through the summer.  Roadside signage will be posted to warn drivers of the upcoming closures.

Cheatham Hill Road Closure: Kennesaw Mountain Pedestrian Improvements/Cheatham Hill Multi-use Trail (Cobb DOT Project X2404 – Districts 1 & 3)

This project includes construction of three multi-use trail segments along Whitlock Avenue, Cheatham Hill Road, and Burnt Hickory Road. The project is a collaborative effort among several local, state and federal agencies, including the Cobb County Department of Transportation, City of Marietta, National Park Service, Federal Highway Administration and the Georgia Department of Transportation.

Construction of the Cheatham Hill Road segment will require closing Cheatham Hill Road between Ward Creek Drive and Cavan Drive for the relocation of a 36-inch water line. The closure is expected to start on June 1, 2021 and last until August 2, 2021. For more information on this project, please visit https://www.cobbcounty.org/transportation/projects/updates.

Image
Picture of map showing closure location

Willeo Road Closure: Willeo Road over Willeo Creek Bridge (Cobb DOT Project X2122 – District 2)

This joint project with the City of Roswell includes a complete replacement of the existing bridge over Willeo Creek located on Willeo Road between Bywater Trail and Timber Ridge Road/Lower Roswell Road at the Cobb/Fulton County line. Construction will require a 4-month closure of the bridge, which is expected to begin June 1, 2021 and last until September 29, 2021. For more information on this project, please visit https://www.cobbcounty.org/transportation/projects/updates.

Image
Map of Willeo Road closure

Barnes Mill Road “Rolling” Closure: Blackjack Mountain Water Main Replacement (Cobb County-Marietta Water Authority Project – District 3)

The Blackjack Mountain Water Main Replacement project area stretches from I-75 and Barnes Mill Road to the Quarles treatment plant on Lower Roswell Road. The current stage of construction will require a “rolling closure” along Barnes Mill Road from the Merritt Road/Wallace Road intersection to Cedar Bluff Way. The rolling closure will start June 1, 2021 and last through July 30, 2021. The detour will route traffic along Wallace Road, North Marietta Parkway/SR 120 and Roswell Road/SR 120 to avoid the area.  For additional project information please contact project hotline at (770-514-5201) or email (blackjack@ccmwa.org).

Image
Map of location of road closure